WATER CAPITAL IMPROVEMENT PLAN

 

TOTAL COST

YEAR

1.

25 HP Submersible pump for California St. well                 DONE $6,500 99-00
2. Rehabilitate and Video Broadway well                               DONE $17,000 00-01
3. Upgrade Mason Road Well                                               DONE $3,000 00-01
4. Connect Mason Water and City Water on Hwy 339          DONE $50,000 00-01
5. Install Radio Telemetry on Mason tank and pump controls  DONE $23,000 00-01
6. **Replace steel water line in Mason System                       DONE $4,500,000 01-02
7. Replace 1940's motors - Mt. View & Broadway wells       DONE $50,000 01-02
8. **Main line extensions in City Water System (Includes Engineering) $1,064,000 01-02
    $5,713,500

**  Anticipate Grant Funding